Point of Beginning

The client wanted a granite bound

May 1, 2009

Posted By donald poole on 5/1/2009 at 12:41 PM

So that was yesterdays chore, setting two granite bounds for the client in Brockton, about 1.5 hours away from my office.
Of course one of them fell in the pavement and an abutting parking lot for a playground.

Using the hammer drill and an invertor I drilled the square slightly larger so I could use the post hole diggers to get the bottom dirt out.

The bound is 4" x 4' and 3ft long.

In Progress
Photobucket

Completed with the origianl PK nail and pavement.
Photobucket

Boy was my back sore after dealing with that!!!!


To read the rest of this thread go to www.i-boards.com/bnp/pob/messages.asp?MsgID=1405807&ThreadID=133230&IsResponse=False#1405807.