Tough Work in a Tight Spot
by Craig Dylan
April 1, 2010
|
|
| Pedestrian
tunnel and sheet piling adjacent to BNSF rail tracks. |
|
EVS completes a tricky staking and monitoring job while dodging trains.
Each day, thousands of commuters navigate the
corridor between Minneapolis and Big Lake.
Served primarily by Interstate 94 and U.S. Highway 10, the route has become
increasingly congested over the past decades.
Several Minnesota governors and other high-level advocates have pushed for a
commuter rail system for years. Minnesota Department of Transportation
officials also believed that commuter rail was the best way to handle the
increasing load. They estimated that building a rail system would be one-third
the expense of upgrading existing highways. Still, cost was always an issue for
legislators.
 |
| EVS
crew member Rob Stern marks the Main II track for movement. |
|
A
significant cost breakthrough came when it was decided to use existing
Burlington Northern Santa Fe Railway (BNSF) lines and rights-of-way rather than
installing an entirely new rail corridor. Under the operating agreement, BNSF
owns the infrastructure and the Metropolitan Council, the agency providing
essential services to the Twin Cities’ metropolitan area, owns the rolling
stock. But using existing lines came with its own set of challenges. It meant that
railroad sidings would have to be added to allow commuter trains and freight
trains to pass each other. Additionally, the commuter system’s stations,
platforms, parking lots and pedestrian access tunnels would have to be
shoehorned into extremely tight footprints already crowded with existing
freight lines.
EVS Inc., of Eden Prairie, Minn., was contracted by Lund Martin Construction to
provide construction staking and monitoring services for the new Northstar
Commuter Rail station, which would be located in Fridley, Minn. “The site was
less than a mile from one of BNSF’s big switchyards,” says Michael Williams,
EVS survey office manager. “Five tracks ran through the site, and the freight
train schedule didn’t slow down while we were working. There was about one
train per hour during the day, sometimes more, coming through at 20 miles per
hour. And sometimes trains would park in the middle of the site for several
minutes. Since we had to stay in a ‘clear zone’ during those times, we did a lot
of waiting.”
The BNSF team was understandably concerned about safety. They required EVS
personnel to complete rail safety certification services, and they provided
flagmen for all working hours. They were also concerned about possible damage
to existing lines. Tunneling, earth moving and trenching were taking place near
the rails, and even very small shifts in rail alignment can be disastrous for
heavy, fast-moving trains. BNSF officials were interested in any movement over
3/4-inch. “Monitoring was a big deal,” Williams says, “because nobody could get
started without it.”
 |
| EVS
Crew Chief Stan Barthel adjusts a Trimble S8 Total Station in preparation for
monitoring. |
|
Keeping
a Close Eye on the Rails
Pedestrian tunnels had previously been placed beneath lines at Fridley, but elevator shafts and some trenching
were still required. In some places, excavation was within 2 feet of active
rails, which had to be shored up with a steel sheet and tieback system. EVS was
asked to install a 24/7 monitoring system that would automatically alert
officials when any rail moved beyond the 3/4-inch threshold. “We’ve done
monitoring before, but not so automated as this,” Williams says. “So there was
a bit of a learning curve.”
The EVS crew knew it wanted to work with Trimble’s 4D Control software, which
takes advantage of the Trimble S8 Total Station’s monitoring capacities and
works with Trimble Survey Controller field software to create custom monitoring
solutions. In this case, the crew planned to establish a permanent S8 setup
onsite and program it to automatically shoot monitored points every hour.
Simple enough in concept--but the devil, as they say, is in the details.
For one thing, where exactly--in a crowded, unfenced railroad project--does one
place a critical precision instrument so that it can be left overnight and have
sight lines to all necessary points? After much consideration, EVS Crew Chief
Stan Barthel found a good spot. “There weren’t many options,” he says. “There
were deep excavations, as deep as 20 feet. There were right-of-way issues, and
the soil was mostly sandy and granular, which meant that vibrations from trains
and construction would radiate through the soil to our setup.”
 |
| A section of track is repaired after movement
is detected. |
|
The
EVS crew ended up digging a hole 4 feet deep, pouring concrete and setting a
6-by-6-inch wooden post. There was still movement, so four guy wires were
added. Then a platform and scaffold were built, with a plywood roof to offer
some protection from the elements. “Wind-driven rain was a concern, of course,”
Barthel says. “But since we needed about 160 degrees of clear sight for the
observations, there wasn’t much we could do about it.” The instrument ended up
about 10 feet above the ground, offering some protection against theft and
tampering, and the tribrach-set screw was replaced so that an Allen wrench was
needed to adjust it.
Even with all that effort, Barthel wasn’t sure the setup would work. “The
closest rail, just 35 feet away, had a joint in it, and when trains hit that
joint you could feel it a hundred feet away. We did have to re-level a few
times. But, overall, things worked out.”
Since there was no permanent power supply for the first month of the project,
deep-cycle car batteries were used to power the total station. These were
switched out weekly. A Wi-Fi-enabled computer, powered by a generator, was kept
in a nearby field office. Wi-Fi was needed so that the 4D Control software
could send e-mail alerts as needed. Communication between the Trimble S8 and
the onsite computer was by radio.
 |
| A
Trimble S8 Total Station monitors the tracks as a BNSF train rolls past. |
|
With
the setup established, the EVS crew then set out 72 peanut prisms on
L-brackets, which were attached to the tracks with construction adhesive.
“After you shoot the targets the first time,” Barthel says, “the S8 remembers
and can then shoot them all automatically on a schedule, which in this case was
every hour. It took about 20 minutes for a round of shots.” Even with the high
setup, prisms were often blocked by trains or equipment. The Trimble S8 and 4D
Control handled that by skipping blocked shots when the first attempt failed
and returning to missed shots at the end of a cycle. “The S8 was amazingly
fast,” Barthel says.
With the help of Frontier Precision Inc., the EVS crew was able to set up the
monitoring exactly as required for this project thanks to the software’s
capabilities. “All in all,” Williams says, “it’s powerful software that did
everything we needed it to do.”
When there were shifts in position of more than 3/4-inch, the software sent
e-mail alerts to the crew. There were a lot of these at first until Barthel
figured out that normal train activity caused a lot of movement. “When trains
move through, the track slides in the direction the train is going,” he
explains. “And after the train passes, it settles back into position.”
Fortunately, Barthel was able to set different tolerances for different axes of
movement. “Since we were more interested in lateral movement and up and down
movement,” he says, “we set the tolerances higher for movement in line with the
tracks.”
This change cut down on alerts, but one important warning did come through. In
the first week of monitoring, ballast shifted near some of the shoring, and
tracks sagged unacceptably. The EVS team alerted BNSF personnel immediately.
Machines were brought in to raise the track, and stabilizing piles and ballast
were reset. No trains passed over the shifting track until it was repaired, and
the shoring held for the rest of the project.
EVS ran the monitoring full time for three and a half months with no
significant outage of service. “This type of monitoring is more common in
mines, and this may be the first time it’s been used by a railroad,” Williams
says, “but now that BNSF has seen it in action, they’ve said that they may
start requiring it more often.”
 |
| Track
movement is noted after a train passes by. |
|
Staking
in Crowded Conditions
By coincidence, the EVS crew had done the design survey work for this site in
2005. They found four control points still in place from that work, and they
quickly got on basis. After locating the tunnels and laying out elevator-shaft
entrances, they adjusted the plan grid for the station platforms to match the
as-built tunnel location. This required shifting station plans several tenths
of a foot north while maintaining platform alignment parallel to existing
tracks.
A Trimble R8 GNSS receiver and base station were used to lay out storm sewers,
catch basins, rough grading and light poles. A Trimble 5603 Total Station was
used for all other staking chores. Stakeout points were taken from CAD files,
processed with Trimble Geomatics Office software and loaded into the total
station’s faceplate.
The BNSF-provided flagmen were in contact with the dispatch office at all
times, and incoming trains communicated directly with them, as well. When
trains came through, the EVS crew had to move to clear zones while they were
onsite. “We tried staying far enough away that we didn’t have to take down the
instrument when trains came through,” Barthel says. “But we definitely had to
check our setups after each one. Sometimes we had to reset, but not too often.”
 |
| The
completed Fridley Station for Northstar Commuter Rail. |
|
Innovative
Thinking
“Nobody could really tell us how to do this,” Williams says. “Setting the S8 up
on a tower, leaving it on 24 hours a day, leaving it unsecured overnight--it
was all new to us, and we felt like we had to learn it as we went along.” One
big issue at the beginning of the project was liability for a damaged or stolen
instrument. Ultimately, Anoka
County officials agreed
to take responsibility, but no surveyor ever wants to lose an instrument.
Fortunately, no losses occurred during the project.
The Northstar Commuter Rail Line began service on Nov. 16, 2009, and is
expected to serve 5,600 commuters each day in 2010. By taking a chance,
learning to use new tools and software, and coming up with innovative ideas
such as perching a survey instrument on a 10-foot pole for three and a half
months, EVS was able to build a key component of an important transportation
system--without disrupting existing rail service.
|