Changing the Channel
by Matt Freeman
March 1, 2010
|
|
| The
Wimmera Mallee Pipeline will supply much-needed water to the region while
conserving approximately 100 billion liters previously lost to evaporation and
seepage each year. Photos courtesy of GWMWater |
|
LiDAR and GIS fast track Australia’s Wimmera Mallee Pipeline Project.
As early as the 1890s, there had been talk of
replacing the inefficient Wimmera Mallee open-channel system with a
more-effective pipeline network that would provide a sustainable water supply
to northwestern Victoria, Australia. But it was just talk--a pipe dream for the
dryland farming and rural region extending from the Grampian Mountains in the
south to the Murray River some 300 kilometers
north.
Throughout the 20th century, despite its inefficiencies in supporting the
area’s agriculture, the channel system was extended, branching out for a total
of 17,500 kilometers (10,800 miles) in length. Meanwhile, the earthen channel
system continued to draw water from already taxed sources such as the Wimmera
and Murray rivers; reservoirs in the Grampians; and Victoria’s largest
freshwater lake, Lake Hindmarsh. Add six years of below-average rainfall at the
turn of the century, regional reservoirs at less than 10-percent capacity, and
a highly dysfunctional channel system, and the result was a dryland region that
could no longer sustain agriculture or prosperity.
Studies
done in the late 1990s showed that of the 120,000 megaliters released into the
channel system in an average year, only 17,000 or fewer were actually used by
customers. The rest was lost to evaporation and leakage from the channels and
farm dams.
By the year 2000, it became evident that the 100-year-old pipe dream needed to
become a reality, and it had to happen quickly. Without a new pipeline system,
the Wimmera Mallee region’s production of livestock, wheat, barley, canola,
field peas, chickpeas and faba beans would cease to exist, not to mention the
towns and businesses in the area, which required water to survive.
Members of the community and a steering committee heavily lobbied for a
pipeline. Yet it was not until 2005 that the Commonwealth of Australia and the Victoria state
government reached an agreement on the funding of the Wimmera Mallee Pipeline
Project (WMPP). In the same year, it was announced that Grampians Wimmera
Mallee Water (GWMWater) would be responsible for the delivery of the estimated
10-year project. But those with livelihoods at stake had to wonder if a
completed pipeline in 10 years would be too late.
 |
| An
example of the 2-meter hillshade elevation grid created using ESRI ArcGIS data
processing tools. Visible features include redundant on-farm storage dams as
well as the open-channel network. |
|
Let
There Be LiDAR
Before GWMWater could start designing more than 5,592 miles of pipeline and
building 40 pump stations, it had to undertake a time-intensive environmental
analysis and survey of more than 4,530 square miles of land. The existing 10-
and 20-meter contours and 1:25,000- and 1:50,000-scale line mapping available
for most of the region was completely inadequate for this challenging and
ambitious engineering project.
GWMWater knew that it would not be feasible to rely on photogrammetry and
surveyors alone to capture and analyze the required data for such a large and
diverse terrain. Additionally, the massive amount of resultant survey data
needed to come in a format that would work with the ESRI GIS-based software
platform that GWMWater had launched to manage the project. And every phase of
the project had to move quickly. “The original 10-year construction plan was
based on our experience with the Northern Mallee Pipeline Project, a much
smaller pipeline, and on the proposed funding arrangements with state and
federal governments,” says Jeff Rigby, GWMWater managing director. “However, we
knew we needed to fast track the project in response to the drought
conditions.”
 |
| An
example of the 2-meter grid ALS thinned ground data, which was
processed with ESRI ArcGIS 9.2. |
|
The
search for the right solution led GWMWater to AAMHatch, an Australian-based
firm specializing in geospatial services and products. Rigby believed that
significant efficiencies could be gained by using LiDAR-based imagery of the
entire project area packaged in GIS spatial datasets, and AAMHatch possessed
the LiDAR experience to make it happen. “The scale of the WMPP required ‘smart’
management of project data,” Rigby says. “LiDAR and GIS provided the
opportunity for efficient sharing of data through complex planning processes,
iterative design negotiations, tender and contract management.”
According to Rohan Potter, AAMHatch geospatial consultant and project manager,
the size of the firm’s aerial survey fleet and IT infrastructure combined with
its skills in data processing, management and terrain product creation in the
ESRI environment were the primary reasons AAMHatch was chosen for this time-critical
project. “AAMHatch prides itself on delivering projects that are large and
technically challenging,” Potter says. “This project certainly provided these
opportunities!”
 |
| ArcGIS
terrains provide optimized performance at multiple resolutions through the use
of terrain pyramids that quickly retrieve only the data needed for the required
level of detail in a given area of interest. |
|
Covering
New Ground
Vast volumes of data require careful data management and backup procedures to
maximize efficient processing. Traditionally, elevation data have been supplied
as an ASCII point file, an ESRI shapefile or a triangulated irregular network
(TIN). However, these datasets are time consuming to create, load and analyze,
and they have large storage requirements. For example, every 1 gigabyte ASCII
file equates to a 2.5 gigabyte shapefile or TIN. Additionally, this process
relies on a tile-based approach (generally comprising 2-by-2-kilometer tiles)
that limits the number of points that can be used per file. And the file size
recommendations are restricting--less than 3 million points per shapefile or 12
million points per TIN.
AAMHatch was determined to improve these capabilities for the WMPP. Prior to
gathering the data, the firm worked closely with ESRI software developers to
test and enhance the ArcGIS 9.2 software for large datasets. The solution was
ESRI’s terrain dataset--a multiple-resolution TIN-based surface built from measurements
stored as features in a geodatabase. ArcGIS terrains provide optimized
performance at multiple resolutions through the use of terrain pyramids that
quickly retrieve only the data needed for the required level of detail in a
given area of interest. Having all these data in a GIS would prove crucial in
project workflows and data sharing since the range of people accessing the WMPP
GIS data varied from design engineers, planners, contractors and government
agencies to auditors, project managers, field inspectors, land officers, and
environmental and cultural heritage advisors. The resulting dataset would be
seamless, and the file sizes would be easily manageable--a 1 gigabyte ASCII
file or 200 megabyte Multipoint file becomes negligible in terrain.
Armed
with multiple Optech LiDAR units and Intergraph large-format digital cameras,
six two-person air crews in three aircraft worked day and night to capture the
data and verify successful coverage. While the data-capture team gathered the GPS
and airborne laser scanner (ALS) data, analysts processed LiDAR data for other
geographic areas and generated derived GIS products along with terrain datasets
of the project area comprising 1.3 billion points. Within 10 weeks of beginning
the ALS data capture, AAMHatch was delivering digital terrain models (DTMs) of
approximately +/-15 centimeters vertical accuracy at one sigma (standard
deviation) on open areas with an average laser strike spacing of 1.3 meters--a
significant improvement over the previously available data.
The data were delivered in more than six phases so that GWMWater and its
contractors would receive components of the data as they became available. The
terrain data were complemented by orthoimagery with 60-centimeter image
resolution. Stored in the WMPP GIS, the LiDAR and orthoimagery data provided a
current view of the land use, land cover, and terrain--all data that are
essential for engineers working on the project. At the time, the spatial
foundation dataset was the largest single-file terrain dataset ever produced in
Australia.
The terrain data were easily and quickly processed and analyzed using the
ArcGIS Server 3D extension. By generating terrain products and terrain files
that were one-fifteenth the size of standard files, a savings of more than 20
days in data-processing time was achieved. “These capabilities significantly
improved access, display, performance and analysis of LiDAR data and the
elevation information these data represent,” Potter says.
The first pipes were laid in November 2006. Thanks to the use of LiDAR and
advanced GIS capabilities, the WMPP is on schedule to be completed this
year--five years earlier than originally projected. “There is no doubt that
LiDAR technology enabled AAMHatch to deliver project data in reduced time,”
says Bruce Van Every, PhD, GWMWater project director. “There were significant
efficiencies gained through improved survey processes, accuracy of data, and
the ability to share the data with a range of stakeholders through our GIS.”
When finished, the pipeline will supply stock and domestic water to 7,000 rural
customers and 36 towns across the Wimmera Mallee region and save approximately
100 billion liters of water each year. “It is an enduring legacy of the
project,” Rigby says, “a valuable resource for planning and development for the
whole region.”
Sidebar: Channeling the GIS Data Flow
The
Wimmera Mallee Pipeline Project is one of the largest engineering initiatives
currently under way in Australia. It spans an area of 11,700 square kilometers
and aims to increase the efficiency of water distribution in the Wimmera and
Mallee regions through pipelines and pump stations. GIS not only provided the
required data for the design and construction phases of the WMPP but also was
used to track and record ecological, soil, vegetation, and cultural heritage
information; cadastral and landowner contact details; and lengths of pipes and
valve types. More than 250 layers of GIS data were used with a total volume of
approximately 1 terabyte.
GIS data continue to be a valuable resource for stakeholders. For
example:
• Land liaison staff use
GIS-based maps and aerial photography as they travel throughout the project
area negotiating land access agreements with each landowner.
• Landowners can also access
maps and aerial photography of their properties and the pipeline’s route at the
project’s Web site. Supported by ArcGIS Server software, the Web site includes
layers of data such as land parcels, 1-meter contours, elevation surface,
topography, and channels and dams.
• GIS also makes for good
relationships with project stakeholders. Data sharing between organizations has
been critical in achieving the shortened timelines for the pipeline planning,
approvals and construction.
• As a majority of the 18,000-
kilometer channel system will be filled in, landowners will use GIS data and
maps to plan and rehabilitate the land, returning the disappearing channels to
productive agricultural use.
• Once completed, the
operations, maintenance, and financial and asset management of WMPP will rely
on GIS.
|
By: Nazib Faizal
Posted: April 27, 2010 4:54 AM
Thanks
By: mengesha
Posted: July 13, 2010 9:19 AM