A Winning Bet
by Christine Grahl
January 27, 2009
 |
| The
Las Vegas Convention Center at night. Photo courtesy of the Las Vegas News
Bureau. |
|
A strategic alliance gives surveyors an edge in the Las Vegas Convention Center renovations.
When the Las Vegas Convention and Visitors
Authority (LVCVA) board of directors decided to embark on an $890 million
project in 2005 to provide a face-lift to the Las Vegas Convention Center, they
didn’t fully anticipate the challenges of working with the existing structural
grid system. Originally built in the late 1950s, the convention center had been
expanded over time through the addition of new exhibit halls and meeting rooms
and consisted of three major building components: a North Hall, a Central Hall
and a South Hall. The visionary design for the newest renovation, crafted by
master architect HNTB Architecture, involved a new Grand Concourse that would
join the North Hall to the Central Hall and South Hall as well as an enclosed
pedestrian bridge that would connect the monorail station to the convention
facility. The renovation would also expand and renovate the meeting room
facilities and make other site improvements designed to enhance the overall
experience of visitors.
However,
in the course of compiling the plan backgrounds of the existing facility, HNTB
encountered a problem. While partial construction drawings were available for
each of the buildings, there was no single unified floor plan or structural
grid system that combined all of the building plans into one. Trying to piece together
the record drawings with an ALTA survey revealed significant dimensional
discrepancies--as much as 8 feet in some cases. To move forward with the
proposed renovation, a more accurate approach was needed.
The LVCVA project team contacted a number of local surveying firms and were
impressed with Heritage Surveying based in Las Vegas. Then, at the 2007
American Institute of Architects National Convention, one of the LVCVA project
team members stopped by the exhibit of Irvine, Calif.-based Architectural
Resource Consultants (ARC), a firm that specializes in as-built surveys. The
exhibit featured a laser scanner that was on display through a partnership
between ARC and Optira Inc., a specialist in high-definition as-built
documentation headquartered in Omaha,
Neb. After discussions with ARC
and Optira, LVCVA and HNTB agreed that obtaining 3D models of the above-ceiling
plenums as part of a comprehensive as-built
survey would provide an effective way to unify the structural grid. However,
the project management team wanted to keep Heritage Surveying involved in the
project. The LVCVA made a request: Would the three firms--ARC, Optira and
Heritage Surveying--be willing to work together to complete the as-built
surveys?
Defining the Boundaries
 |
| Renderings
of the renovated Las Vegas
Convention Center. Images
courtesy of HNTB Architecture. |
|
Eager for the chance to take on the project, the firms agreed to explore a
possible collaboration. ARC and Optira had worked together on previous projects
and bid on the Las Vegas
Convention Center project
together. Both companies thought it would be a good opportunity to go in as a
team since each firm had strengths in different areas. However, neither firm
had any experience working with Heritage Surveying.
John Russo, AIA, president and chief executive officer of ARC, and Tim Beck,
PLS, project manager for Heritage Surveying, admit that they were both a bit
skeptical at the outset. “My initial thought was that I didn’t know these
guys,” Russo says. “How were we going to establish a compatible work flow? What
quality of a firm were they?”
Beck
notes that quite a bit of communication and back and forth took place before
they had a signed contract. “We had been working on a full-blown proposal for
the whole project,” he says. “But once we were introduced to John [at ARC] and
were led in that direction, we realized that they had more expertise in the
scanning portion and that we would be better off working closely with them than
trying to fight for the contract.”
Indeed, the alliance would prove crucial to meeting the project requirements.
As negotiations among the three firms progressed, the LVCVA decided that the
project would need to be completed in just three months. Additionally, the
firms would have to conduct the surveys for the 3.2 million square foot
property while all facilities remained fully operational, which would make
access difficult. Precise planning and clear communication would be
paramount.
Fortunately, all three firms had experience handling difficult projects, and
each company brought a high level of skill and integrity to the table. After a
number of in-person meetings and conference calls, ARC, Optira and Heritage
Surveying felt confident that they would be able to work together.
They quickly outlined a plan for dividing the project. Heritage would establish
a control network across the entire site and then bring that network into the
buildings. The firm would also conduct as-built surveys for the exterior
building shells, the primary road adjacent to the convention center (Desert Inn Road)
and the monorail. Optira was given responsibility for conducting the
above-ceiling plenum scans and creating 3D CAD models of existing conditions.
ARC, as the prime contractor, would be the main liaison with HNTB and would
coordinate between the teams. The firm would also architecturally document
as-built floor plans of the complete structure and tie in the existing
structural grid system, which included locating the interior columns and
establishing the architectural grid lines. Deliverables would include 2D
building floor plans, a unified structural grid system and 3D above-ceiling
plenum models.
Fitting the Puzzle Together
 |
| Surveyors
use a laptop interface that allows shots to go straight into CAD, which
eliminates the need for
office processing. |
|
With a basic outline in place, the teams began their work in September 2007. But the project wasn’t always clear-cut. “We’re all experts in a certain discipline,” Beck says. “ARC is an architectural firm. We’re professional land surveyors, and Optira is a laser scanning expert. Tying all three of those different entities together to put our data together was a challenge.” To further complicate the situation, the LVCVA also required the new data to be on the same rotation and fit within the boundary of the existing title survey. “That was a really big piece of the puzzle,” Beck says. “It required a significant amount of both field and office work for everyone involved.” Heritage Surveying was the first team onsite. Using Trimble S6 3 robotic total stations along with Nikon auto and digital levels, four two-person survey crews retagged the boundary points related to the original boundary and set the exterior control around the site. According to Beck, this part of the project took about a week to complete. After the exterior control was established, four two-person teams from ARC began their work, which started with the shell of the buildings. “We tied into the control network and then started shooting the shell using Leica TPS405 total stations along with Leica’s fieldPro,” Russo explains. The ARC teams then moved inside the buildings and started shooting the grid system and walls. By using fieldPro, ARC was able to shoot all of its measurements straight into AutoCAD onsite. “We knew everything was closing and working properly; we were drawing in real time and were able to walk offsite with a 90 to 95 percent complete product in 2D. It was tremendously time efficient,” Russo says.
 |
| Survey
crews from Heritage Surveying establish the control boundary around the South
Hall. |
|
While
ARC’s teams worked on the inside, three crews from Optira began the
above-ceiling plenum scans using two Leica HDS4500 laser scanners and a Leica
HDS3000 laser scanner. ARC crews shot control for the scans using a Leica
TCRP1203R total station. Simultaneously, the Heritage Surveying crews returned
to the site and ran their own network with GPS (using Trimble 5800 GPS
receiver, a Bluetooth-enabled Tripod Data Systems Ranger 500x and TDS Survey
Pro software) to tighten down the network they had established through
conventional methods.
To coordinate their efforts, the teams held weekly planning meetings with HNTB
and the LVCVA in which they outlined a daily strategy for accomplishing the
following week’s work. Flexibility was crucial. “We knew with pretty good
certainty which halls would be filled each day, but the meeting rooms were
tough,” Russo says. “They would have numerous conventions, conferences, etc.,
going on all at the same time. We had to roll with it and be able to change our
plans as needed.”
 |
| A
survey team uses Leica HDS technology to scan the inside of the South Hall. |
|
According
to Russo, having three different firms working together on the project was key
to achieving the required flexibility. “There were a number of times when the
convention center housekeeping staff inadvertently threw away our control
points. To be able to call Tim and say, ‘Hey, we lost some points here,’ and
have him send a guy out right away to reset the point was fabulous and allowed
us to hit our deadline,” Russo says. “Our scope crossed over numerous times. If
it started to get too far out of bounds, then we would say ‘Hey, I may need to
talk to you about swapping some money here.’ But everyone was good with
that.”
“Logistically, you’d think that you would always run into problems when you’re
working with a company you’ve never worked with before,” Beck says. “But all three
of us went out of our way to make the other firms feel comfortable, and it was
a great work environment.”
 |
| Point
cloud data of an above-ceiling plenum scan. |
|
The
collaboration proved beneficial for quality control, as well. Several times
during the project, the teams met online through a Web meeting hosted by Optira
and compared all three data sets--the 3D scans and CAD models from Optira, the
control network data from Heritage Surveying and the 2D AutoCAD data from ARC.
Any variations were immediately obvious. “We overlaid and compared all those
data sets and were able to work out a lot of kinks before we had to turn those
data sets over to the client,” Russo says. “If two of the data sets were in
agreement and one was out, you could assume that [the odd set] was suspect
data. We would then verify that the two similar readings were, in fact,
accurate. It was a great three-way validation of accuracy.”
“The ability to bring all three firms’ data sets into a common format (Autodesk
Navisworks) and common forum (the online meetings) significantly strengthened
our ability to work collaboratively,” adds Mitch Schefcik, president and chief
executive officer of Optira.
The Future of Surveying
 |
| A
plenum model derived from point cloud data and
modeled in Autodesk Architecture. |
|
The project was completed on time and on budget and has caused all of the firms
involved to rethink the way they do business. “With the economy, everything is
shrinking,” Beck says. “We like to take the approach that we can accomplish
anything, but right now, it’s all about who you know and who you work with and
being as efficient as you can.”
Russo agrees. “Knowing our strengths and weaknesses helped us to understand
where it made sense to divide our scope of work between our three firms so that
we each focused on what we were experts in,” he says. “This was critical to the
success of the project.
 |
| A plenum model fully rendered using
Navisworks. |
|
“I
believe the business model for the future is to create a core team of experts
within an organization and strategic alliances with other firms and individuals
with whom you can pursue opportunities in a team approach,” he adds. “The
result is a much more powerful and knowledgeable team with a tremendous
competitive advantage that can scale up or down in size to go after both
large-scale opportunities and high-volume opportunities without the burden of
carrying all the overhead of a larger firm. The Las Vegas Convention Center
project proved, in my mind, that this model works.”
Editor’s note: ARC, Optira and
Heritage Surveying were
awarded second place in POB’s 2008 Highlights in Surveying contest for their
roles in the Las Vegas Convention Center project. To enter a project in the
2009 contest, visit his.pobonline.com. The deadline is Feb. 16.
|